Teignbridge

Projects / Works / Schemes Lead Authority Study, Design or Works

2018/19 DCC Contribution
£

2018/19 DCC Flood Prevention
£
Other Funding Sources £  Details of Proposal
Stokeinteignhead DCC D/W  50,000  50,000 330,000

 

Finalise detailed design, develop and submit Business Case to secure Defra FDGiA and commence construction of the essential flood improvements

Teignmouth 30,000 Review of SWMP and consider flood improvement options

Recent and Current Work

The following case studies have been prepared to highlight some of the excellent work that has been achieved, is being developed, and the different opportunities that have been adopted for funding the schemes.