South Hams

Projects / Works / Schemes Lead Authority Study, Design or Works 2018/19 DCC Contribution
£
2018/19 DCC Flood Prevention
£
Other Funding Sources £  Details of Proposal
Modbury Flood Management Scheme DCC D/W  40,000 37,500 625,000 Construction phase of essential flood improvements. Works to be completed within 2018
Ivybridge Flood Improvements SHDC D/W  50,000 75,000 150,000 Completion of detailed design and business case to secure FDGiA and deliver construction phase for the essential flood improvements
Chillington DCC W  40,000 25,000 65,000 Delivery of construction phase to provide improved drainage and reduction in flood risk.
Kingsbridge Study SWW S  20,000 Ongoing study and hydraulic modelling in partnership with other RMAs. Develop options and progress to detailed design.
Dartmouth EA S 10,000 Ongoing investigations and scheme optioneering in partnership with SWW and EA. Contribution set aside to support further modelling by the EA
Ugborough DCC D/W 30,000 20,000 25,000 Finalise detailed design of flood improvements and subject to funding approval for cost beneficial scheme, deliver construction phase for catchment.
Frogmore PC W 25,000 Contribution towards flood improvements being led by the Parish Council in partnership with the local landowner
East Allington Asset Designation DCC 1,000 Designation of weir structure to prevent rebuilding of wall