Exeter

Projects / Works / Schemes Lead Authority Study, Design or Works

2018/19 DCC Contribution

£

2018/19 DCC Flood Prevention
£
 Other Funding Sources £ Details of Proposal
Exeter Surface Water Improvements – Design DCC D 50,000 50,000 100,000 Preparation of Business Case for Phase 1 Flood Improvements on the Northbrook catchment with start of construction, subject to funding approval.
Topsham Flood Improvements ECC W 20,000 Contribution to Exeter City Council towards surface water element of proposed flood improvement works. This is a long standing commitment carried over from previous years and subject to a cost beneficial scheme being deliverable.

Recent and Current Work

The following case studies have been prepared to highlight some of the excellent work that has been achieved, is being developed, and the different opportunities that have been adopted for funding the schemes.