Clyst Heath Primary School – Replace water cylinder

Decision Taken:

Approved

Summary of Reason(s) for Decision Taken:

We are requesting an additional £9,000 for the above project.

This additional cost is due to unforeseen issues with the supports of the high level light-fittings which prevented the pipe boxing removal and were necessary to correct in order to complete the works.

Authority is requested to increase the allocation for this project by £9,000, funded from savings on the Sports Hall project at The Park School Barnstable.

Please click on this LINK

Summary of Alternatives or Options considered and rejected:

None

Details of any conflict of interest and dispensation granted to the Officer taking the decision or by any Member of the Council in delegating responsibility for any specific express delegation:

None

Contact for enquiries/further information:
Chris Dyer
Decision Date:
15 December 2016

A copy of this decision and any supporting documentation considered by the Officer taking this decision may also be made available or inspection by the public at the Council’s Offices or posted upon payment of any copying and postage charges. Any member of the public wishing to take up either of these options is asked to please ring 01392 382888 or email: members.services@devon.gov.uk