Chief Officer for Highways, Infrastructure Development and Waste - Meg Booth

Summary of Matter or Issue Requiring Decision:

St Michael’s C of E Primary, Kingsteignton – Block 01 Roof improvements

 

Decision Taken:

Approved

Summary of Reason(s) for Decision Taken:

The sum of £70,500 has already been approved for this project. Following commencement of works and the full roof strip it became apparent that a number of timber rafters had suffered significant unforeseen water ingress and had suffered sufficient decay that warranted complete replacement. The lead gutter along the effected elevation was found to be cracked and life expired and it has been advised that complete replacement is required to prevent future water ingress. The cost of the additional work is £13,500.Approval is requested to increase the allocation for this project by £13,500 to £84,000 and this will be funded by savings on the boiler replacement project at Kentisbeare C of E Primary.

Please click on this LINK

Summary of Alternatives or Options considered and rejected:

None

Details of any conflict of interest and dispensation granted to the Officer taking the decision or by any Member of the Council in delegating responsibility for any specific express delegation:

None

Contact for enquiries/further information:
Chris Dyer, Built Environments 01392 383000
Decision Date:
6 September 2017

A copy of this decision and any supporting documentation considered by the Officer taking this decision may also be made available or inspection by the public at the Council’s Offices or posted upon payment of any copying and postage charges. Any member of the public wishing to take up either of these options is asked to please ring 01392 382888 or email: members.services@devon.gov.uk