Summary of Matter or Issue Requiring Decision:

Ilfracombe College – Boiler, Roof and Fenestrations

Decision Taken:

Approved

Summary of Reason(s) for Decision Taken:

This project completed back in 2015 and the leftover budget was added back into our Capital Maintenance Pot. NPS has recently received a very late retention claim from the Contractor and having checked their records they have confirmed that it’s correct.

Approval is therefore sought for an allocation of £15,000 to cover this retention. This will be funded from savings on the Axe Valley Community College Replacement Blocks project

Please click on this LINK

Summary of Alternatives or Options considered and rejected:

None

Details of any conflict of interest and dispensation granted to the Officer taking the decision or by any Member of the Council in delegating responsibility for any specific express delegation:

None

Contact for enquiries/further information:
Chris Dyer, Built Environments 01392 383000
Decision Date:
15 January 2018

A copy of this decision and any supporting documentation considered by the Officer taking this decision may also be made available or inspection by the public at the Council’s Offices or posted upon payment of any copying and postage charges. Any member of the public wishing to take up either of these options is asked to please ring 01392 382888 or email: members.services@devon.gov.uk