Work schedule

The schedule below provides an overview of how the work on the new cycle route facilities will be phased. This will be updated once a construction programme is in place.

August to October 2017

Trapping and relocation of the reptiles where works are planned.

October 2017

Setting up the site compound area.

Minor alterations along the eastern side of Cumberland Way and Pinhoe Road.

Removal of permanent road markings, and installation of temporary road markings to realign traffic away from the main works areas on the western side of Cumberland Way.

October to November 2017

Construction in the vicinity of the Hollow Lane junction.

November to December 2017

Construction on Cumberland Way, from Hollow Lane to the Tithebarn Link Road Roundabout.

October 2017 to January 2018

Construction at the Tithebarn Link Road roundabout on Cumberland Way.

December 2017 to March 2018

Construction on Cumberland Way, from the roundabout to the junction with Pinhoe Road/Main Road.

February to June 2018

Construction at the junction of Cumberland Way and Pinhoe Road/Main Road.

April to June 2018

Construction in the vicinity of the Pilton Lane Junction.

June 2018

Removal of the compound and traffic management.