“I require clarification please on the listed highway incident number D183374778 on the road from Trumpeter to Lewthorn Cross, Ilsington.

 Please will you advise what corrective measures were taken following an engineer visit and supply me with the photographs taken on site, preferably before and after corrective action.

 The current status stated says: “Awaiting Measure” but also gives a completion date. This information is clearly inconsistent, please clarify.”

 

Please find here a document, showing a before and after photograph of the defect repair (D183374778) carried out by the contractor.

This work was undertaken on the 30th August 2018, which is, therefore, the completion date.

The status ‘awaiting measure’ is terminology that is used on our system, meaning that the work is waiting to be measured and quantified, before an invoice is submitted from the contractor to Devon County Council for payment.