Bridge Road Improvement Works

The original completion date set

The original Completion Date at the time the contract started was 17th April 2017.  Please note that under the terms of the contract, there is provision to change the Completion Date to account for changes in the work required.

The contractors penalties for not completing the works on this due date 

The Contractor pays delay damages from Completion Date of £3000 per each full day delayed until removal of all traffic management and permanent opening of all 4 vehicle lanes and the footway / cycleway to traffic